Nuclear Power Plant Decommissioning


Plant:
Project:
Unit:
Location:
Owner:
Year:

Dairyland La Crosse Boiling Water Reactor
Reactor Vessel Removal Project
Single Unit Plant
La Crosse, WI
Dairyland Power Cooperative
2005 -2007









Scope:

Bigge Power Constructors, as subcontractor to Duratek, performs the following nuclear power plant decommissioning work involving heavy lift and heavy transportation.

  • Mange the engineering, procurement and construction effort including detail analysis, diamond wire saw cutting of concrete obstacles, removal of the reactor vessel and transportation
  • Manage the Engineering effort including a 50.59 analysis by Bigge subcontractor, ARES
  • Engineer unique solutions for lifts in compliance with 50.59 and NUREG 0612
  • Mange the cutting of an RV removal path through the Bio Shield Wall and Reactor Building Shell by subcontractor Bluegrass Bit Co.
  • Fabricate, furnish, install and operate gantries, lifting devices, and transportation equipment
  • Remove the Reactor Vessel from the Reactor Building
  • Lower the RV to a Duratek transportation canister and seal weld
  • Downend the canister/ RV to transport and trans-load to a rail car for travel to Barnwell

Job Challenges:

Bigge Constructors successfully dealt with the following challenges on this project.

  • Engineering unique solution for lifting in compliance with applicable regulations for spent fuel still resident in close proximity to the Reactor Vessel
  • Managing the regulatory required engineering analysis
  • Handling the RV of 200 tons through a complicated evolution of lifting steps
Bigge Power Constructors
April 4, 2006