Heavy Lifting


Plant:
Project:
Location:
Owner:
Year:

Cobb Station
Electric Generator Exchange
Muskegon, Michigan
GE Energy Services for Consumers Energy
September, 2005 and January, 2005









Scope:

Bigge Crane and Rigging, as contractor to General Electric, performed the following heavy transport and heavy lifting activities at the Consumers Energy Cobb Station Plant:

  • Engineering a custom rigging solution for removal of the plant’s 275 ton Westinghouse electric generator
  • Erected, operated and disassembled a gantry system for trans-loading the new generator from rail delivery
  • Transported the new generator approximately 1 mile by hydraulic platform trailer, lifted the 265 ton generator to the turbine deck and set
  • Moved the old generator to on-site storage

Job Challenges:

Bigge Constructors will successfully deal with the following challenges on this project.

  • Engineering a solution to the transportation and lift issues
  • Handled the 275 ton loads through lifting, rotating and lowering
Bigge Power Constructors
December 23, 2005