Nuclear Reactor Vessel Head Replacement


Plant:
Project:
Location:
Owner:
Contractor:
Year:

H.B. Robinson Unit #2 (702 MW)
Reactor Vessel Closure Head Replacement Projects
Hartsville, SC
Progress Energy
Westinghouse Electric Co.
2005 (October)









Scope:

Bigge Power Constructors, as subcontractor to Westinghouse, performed the following nuclear reactor vessel head (RVH) replacement work involving heavy lift and heavy transportation.

  • Engineered custom solutions for the plant’s head and Containment circumstances, with containment equipment hatch located at grade
  • Fabricated lifting and skidding devices and runways to move the RVH heads
  • Ensured devices account for RVH with CRDM’s attached
  • Ensured devices account for extremely tight clearances through equipment hatches
  • Moved Duratek transportation container into Containment, upended, and placed on RVH
  • Removed the existing RVH from containment inside the Duratek container
  • Installed specialized Bigge handling equipment in Containment including a through-hatch runway system
  • Moved into Containment, upended, lifted and set replacement RVH with CRDM’s attached
  • Transported RVH and Duratek container and trans-loaded for road travel to disposal

Job Challenges:

Bigge Constructors successfully dealt with the following challenges on this project.

  • Engineering unique solution to RVH accounting for CRDM’s, tight clearances and the at grade equipment hatch access
  • Handling, skidding and rotating the RVH with CRDM’s attached
  • Handling and lifting RV heads with CRDM’s attached approximately 150 tons
  • Beating the critical path schedule while achieving low dose and safety
Bigge Power Constructors
Revised July 18, 2005

  Download PDF